Page udated on:
December 29, 2007 | January 24, 2008 | February 27, 2008 | September 29, 2008 |
December 12, 2008 | June 15, 2009 | August 19, 2009 | October 3, 2009 |
December 7, 2009 | March 8, 2010 | February 5, 2011 | September 4, 2011 |
December 10, 2011 | June 6, 2012 | December 3, 2012 | December 15, 2012 |
March 5, 2013 | June 3, 2013 | June 6, 2014 | June 1, 2015 |
July 21, 2015 | March 8, 2016 |
Chapter Status
Color coding | |
---|---|
Completed: | |
In process: | |
Not completed: |
Chapter | Start | End | Time | Notes |
---|---|---|---|---|
Factory | Oct, 2005 | May, 2006 |
Includes:
|
|
Chapter 3 Education |
Aug 15, 2006 | Sep 25, 2006 | ||
Chapter 4 Bulkheads |
Nov 19, 2006 | Dec 25, 2006 | 14:00 | Step 1: Front seat back |
Dec 26, 2006 | Dec 30, 2006 | 19:17 | Step 2: Forward bulkhead |
|
Jan 01, 2007 | Jan 09, 2007 | 21:38 | Step 3: Instrument panel |
|
Jan 03, 2007 | May 15, 2007 | 33:06 | Step 4: Landing gear bulkheads |
|
Jan 04, 2007 | May 19, 2007 | 15:46 | Step 5: Firewall |
|
Chapter hours |
103:47 |
|||
Chapter 5 Fuselage Sides |
May 21, 2007 | May 25, 2007 | 11:35 | Step 1: Jigs & longerons |
May 25, 2007 | May 28, 2007 | 21:20 | Step 2: Fuselage forms |
|
May 30, 2007 | May 31, 2007 | 05:25 | Step 3: Shaping insides |
|
Jun 1, 2007 | Jun 11, 2007 | 13:25 | Step 4: Longerons |
|
Jun 10, 2007 | Jun 16, 2007 | 12:40 | Step 5: Lower longerons |
|
Jun 15, 2007 | Jun 18, 2007 | 13:42 | Step 6: Fuselage sides |
|
Chapter hours |
78:57 |
|||
Chapter 6 Fuselage Assembly |
June 20, 2007 | Sep 13, 2007 | 44:09 | Step 1: Fuselage build |
Sep 14, 2007 | Oct 17, 2007 | 36:49 | Step 2: Keel & brace |
|
Oct 17, 2007 | Oct 30, 2007 | 37:57 | Step 3: Fuselage bottom |
|
Chapter hours |
118:55 |
|||
Chapter 7 Fuselage Exterior |
Oct 30, 2007 | Nov 7, 2007 | 27:00 | Step 1: NACA scoop |
Nov 7, 2007 | Dec 15, 2007 | 23:14 | Step 2: Shaping bottom |
|
Dec 15, 2007 | Dec 23, 2007 | 13:34 | Step 3: Fiberglassing |
|
Dec 28, 2007 | Jan 3, 2008 | 06:55 | Step 4: Shaping sides |
|
Jan 3, 2008 | Jan 24, 2008 | 21:10 | Step 5: Fiberglassing |
|
Chapter hours |
91:53 |
|||
Chapter 8 Headrest & Seatbelts |
Feb 9, 2008 | Feb 9, 2008 | 01:40 | Step 1: Carving foam |
Feb 10, 2008 | Feb 11, 2008 | 07:43 | Step 2: Fiberglassing |
|
Feb 10, 2008 | Feb 14, 2008 | 08:58 | Step 3: Shoulder support |
|
Step 4: Making headrests |
||||
Feb 10, 2008 | Feb 10, 2008 | 01:53 | Step 5: Shoulder harness |
|
Feb 14, 2008 | Feb 17, 2008 | 14:48 | Step 6: Seatbelts & step |
|
Feb 17, 2008 | Feb 23, 2008 | 29:28 | Step 7: Seatbelt attach |
|
Chapter hours |
64:28 |
|||
Chapter 9 Landing Gear & Landing Brake |
Feb 19, 2008 | Feb 26, 2008 | 26:21 | Step 1: Gear bulkhead |
Mar 10, 2008 | Mar 23, 2008 | 29:11 | Step 2: Start strut install |
|
Mar 23, 2008 | Jul 15, 2008 | 78:48 | Step 3: Attach tabs |
|
Jul 17, 2008 | Aug 2, 2008 | 32:41 | Step 4: Landing gear cover |
|
Aug 2, 2008 | Oct 16, 2008 | 27:33 | Step 5: Axles & brakes |
|
Oct 10, 2008 | Nov 1, 2008 | 47:29 | Step 6: Landing brake |
|
Chapter hours |
242:03 |
|||
Chapter 10 Canard |
Jan 23, 2009 | Feb 10, 2009 | 10:25 | Step 1: Cutting the Cores |
Apr 15, 2009 | May 5, 2009 | 31:30 | Step 2; Lift Tabs & Shear Web |
|
May 10, 2009 | Jun 30, 2009 | 10:15 | Step 3: Assemble Canard Sections |
|
Jul 1, 2009 | Jul 5, 2009 | 09:10 | Step 4: Spar Cap Layup |
|
Jul 7, 2009 | Jul 7, 2009 | 06:29 | Step 5: Apply Bottom Skin |
|
Jul 9, 2009 | Jul 24, 2009 | 35:42 | Step 6: Hinges, Spar Cap & Top Skin |
|
Chapter hours |
103:31 |
|||
Chapter 11 Elevators |
Jul 14, 2009 | Aug 3, 2009 | 12:27 | Step 1: Cutting foam cores & bonding to torque tubes |
Aug 4, 2009 | Aug 4, 2009 | 05:29 | Step 2: Installation of the bottom skin |
|
Aug 5, 2009 | Aug 9, 2009 | 11:34; | Step 3: Installation of the top skin |
|
Aug 6, 2009 | Aug 22, 2009 | 19:25 | Step 4: Installing the NC-6 inserts and the NC-3 hinges |
|
Aug 11, 2009 | Aug 27, 2009 | 22:59 | Step 5: Checking the elevator travel & installing tip farings |
|
Aug 27, 2009 | Sep 13, 2009 | 15:28 | Step 6: Install pitch trim belcrank & balance weights |
|
Chapter hours |
87:22 |
|||
Chapter 12 Canard Installation |
Aug 31, 2009 | Aug 31, 2009 | 01:20 | Step 1: Fitting the alignment pins |
Aug 31, 2009 | Sep 4, 2009 | 11:52 | Step 2: Aligning the canard |
|
Sep 13, 2009 | Sep 16, 2009 | 04:28 | Step 3: Fitting elevators & torque tube to fuselage |
|
Chapter hours |
17:40 |
|||
Chapter 13 Nose, Nose Gear & Rudder pedals |
Sep 20, 2009 | Oct 1, 2009 | 05:26 | Step 1: Reinforcing the glass strut |
Oct 16, 2009 | Nov 13, 2009 | 23:01 | Step 2: Fabrication of the NG-30s |
|
Dec 27, 2009 | Dec 28, 2009 | 11:10 | Step 3: Installing the electric nose lift |
|
Dec 29, 2009 | Dec 30, 2009 | 06:54 | Step 4: Installation of the nose box on fuselage |
|
Jan 9, 2010 | Jan 25, 2010 | 48:08 | Step 5: Adding the nose floor and sides |
|
Jan 24, 2010 | Jan 26, 2010 | 06:24 | Step 6: Installing the rudder pedals |
|
Jan 30, 2010 | Mar 30, 2010 | 24:02 | Step 7: Installing the master brake cyclinders |
|
Apr 6, 2010 | Jan 18, 2011 | 30:49 | Step 8: Completion of the nose gear |
|
Nov 16, 2010 | Nov 16, 2010 | 03:12 | Step 9: Piping the pitot & static system |
|
Jan 20, 2011 | Aug 5, 2011 | 78:22 | Step 10: Closing the top & finishing the outside |
|
Aug 5, 2011 | 18:47 | Step 11: Making the door for the nose compartment |
||
Chapter hours |
256:15 |
|||
Chapter 14 Center Section Spar |
Aug 15, 2011 | Aug 18, 2011 | 10:35 | Step 1: Center section jig |
Aug 18, 2011 | Aug 20, 2011 | 3:15 | Step 2: Assembly of foam parts |
|
Aug 17, 2011 | Aug 29, 2011 | 23:40 | Step 3: Interior layups |
|
Aug 23, 2011 | Oct 24, 2011 | 25:46 | Step 4: Install the forward face |
|
Oct 25, 2011 | Oct 29, 2011 | 19:49 | Step 5: Outside hard points |
|
Nov 11, 2011 | Nov 19, 2011 | 13:14 | Step 6: Spar cap layup |
|
Nov 24, 2011 | Nov 28, 2011 | 28:10 | Step 7: Shoulder harness & outside layups |
|
Nov 29, 2011 | Dec 11, 2011 | 6:48 | Step 8: Hardpoint reinforcements |
|
Dec 13, 2012 | Dec 24, 2012 | 17:17 | Step 9: Access for wing attach and end layup |
|
Step 10: Installing in the fuselage |
||||
Chapter hours |
117:48 |
|||
Chapter 15 Firewall |
Step 1: Rudder cable brackets |
|||
Step 2: Firewall insulation & liner |
||||
Chapter hours |
|
|||
Chapter 16 Control System |
Jan 3, 2012 | Jan 3, 2012 | 1:53 | Step 1: Pivot mounts |
Jan 3, 2012 | Jan 3, 2012 | 2:07 | Step 2: Fabrication of pitch & roll parts |
|
Jan 21, 2012 | Jan 21, 2012 | 1:29 | Step 3: Assembly of pitch & roll parts |
|
Jan 21, 2012 | April 5, 2012 | 20:17 | Step 4: Installation of pitch & roll assembly |
|
April 5, 2012 | April 11, 2012 | 18:27 | Step 5: Routing & rigging the rudder cables |
|
April 21, 2012 | Nov 13, 2012; | 10:35 | Step 6: Rudder stop and brakes |
|
Chapter hours |
54:48 |
|||
Chapter 17 Trim System & Center Console |
May 1, 2012 | June 12, 2012 | 15:23 | Step 1: Roll trim |
April 21, 2012 | Oct 30, 2012; | 16:54 | Step 2: Pitch trim |
|
July 10, 2012 | Nov 13, 2012 | 77:20 | Step 3 & 4: Landing brake, center console, throttle quadrant; |
|
Step 4: Throttle quadrant; completed during step 3 |
||||
Step 5: Landing light (Completed in Chap 13; Step 10A.) |
||||
Chapter hours |
109:37 |
|||
Chapter 18 Turtleback and Canopy |
Dec 12, 2012 | Dec 25, 2012 | 25:39 | Step 1: Building the turtleback form |
Dec 25, 2012 | Dec 28, 2012 | 17:52 | Step 2: Construction of turtleback & inside layup |
|
Jan 2, 2013 | Jan 9, 2013 | 29:48 | Step 3: Turtleback bulkhead & rib |
|
Jan 10, 2013 | Jan 17, 2013 | 9:15 | Step 4: Contouring & glassing outside of turtleback |
|
Jan 17, 2013; | Feb 18, 2013 | 20:15 | Step 5: Installing the windows |
|
Step 6: Installing hinges on longerons (skipped (Front Hinged Canopy)) |
||||
Feb 12, 2013 | Feb 13, 2013 | 5:00 | Step 7: Installing upper half of firewall |
|
Step 8: Installing the turtleback (waiting for spar installation) |
||||
Step 9: Engine mount reinforcements (waiting for spar installation) |
||||
Feb 19, 2013 | Apr 7, 2013 | 15:32 | Step 10: Installing the canopy |
|
Apr 8, 2013 | Oct 23, 2013 | 34:37 | Step 11: Building the canopy frame |
|
Oct 22, 2013 | Feb 25, 2014 | 36:00 | Step 12: Carving the inside foam |
|
Apr 2, 2014 | Apr 8, 2014 | 26:18 | Step 13: Canopy hardware reinforcements & inside skin |
|
Step 14: Provision for removable fuselage top (to be skipped) |
||||
Mar 13, 2013 | Feb 10, 2015 | 43:19 | Step 15: Canopy hinges; cutting out frame; install drip rail |
|
Step 16: Installing fuselage top (not needed due FHC design) |
||||
Mar 24, 2015 | Apr 14, 2015 | 18:00 | Step 17: Canopy lip and instrument cover |
|
Step 18: Installing access door (will not be installed) |
||||
Dec 23, 2014 | Nov 4, 2014 | 54:20 | Step 19: Installation of canopy latches |
|
Step 20: Safety catch (skipped, front hinge canopy) |
||||
Jan 20, 2015 | Jan 20, 2015 | 1:30 | Step 21: Canopy handle |
|
Step 22: Canopy stop |
||||
Nov 5, 2013 | Jan 20, 2015 | 60:23 | Step 23: Cockpit ventilation |
|
Chapter hours |
397:48 |
|||
Chapter 19 Wings & Ailerons |
July 5, 2015 | July 7, 2015 | 5:46 | Step 1: Building the wing jigs |
Step 2: Setting up the jigs |
||||
May 19, 2015 | July 14, 2015 | 41:47 | Step 3: Cutting foam cores |
|
Step 4: Assembly of foam cores & lay up of shear web |
||||
Step 5: Bottom spar cap |
||||
Step 6: Bottom skin |
||||
Step 7: Top spar cap |
||||
Step 8: Top skin |
||||
Step 9: Wing ribs |
||||
Step 10: Ailerons |
||||
Step 11: Controls |
||||
Step 12: Attachment, wing to center section spar |
||||
Chapter hours |
|
|||
Chapter 20 Winglets & Rudders |
July 20, 2015 | July 21, 2015 | 14:15 | Step 1: Cutting the cores |
Step 2: Glassing the skins |
||||
Step 3: Jigging upper winglet to wing |
||||
Step 4: Inside layups |
||||
Step 5: Outside layers |
||||
Step 6: Lower winglet attach |
||||
Step 7: Rudder |
||||
Chapter hours |
|
|||
Chapter 21 Strakes & Fuel Tanks |
Step 1: Fabrication of parts |
|||
Step 2: Jigging and assembly of parts |
||||
Step 3: Inside layups |
||||
Step 4: Vent, screen and drain |
||||
Step 5: Top skin cores |
||||
Step 6: End rib and outlet piping |
||||
Step 7: Bottom outside skin and sump |
||||
Step 8: Top skin |
||||
Step 9: Pressure check |
||||
Step 10: Leading edge and outboard fairing blocks |
||||
Step 11: Fuel valve, electric pump and gascolator |
||||
Chapter hours |
|
|||
Chapter 22 Electrical |
|
|||
|
||||
Chapter hours |
|
|||
Chapter 23 Engine |
|
|||
|
||||
Chapter hours |
|
|||
Chapter 24 Covers & Fairings |
Jan 13, 2015 | Jan 19, 2015 | 7:47 | Step 1: Map pockets |
Apr 14, 2015 | Feb 9, 2016 | 36:42 | Step 2: Front armrests |
|
Feb 16, 2016 | Step 3: Front seat thigh supports |
|||
Feb 16, 2016 | Step 4: Rear seat armrests |
|||
Step 5: Heat duct cover |
||||
Step 6: Back seats |
||||
Step 7: Landing brake & battery cover |
||||
Step 8: Canard cover |
||||
Step 9: Strake fairings |
||||
Step 10: Wing centerspar seal |
||||
Step 11 Optional ice shields |
||||
Chapter hours |
|
|||
Chapter 25 Finishing |
|
|||
|
||||
Chapter hours |
|
|||
Chapter 26 Upholstery |
|
|||
|
||||
Chapter hours |
|
|||
Phase 1 Flight Testing |
|
|||
|
||||
Chapter hours |
|
|||
Total Hours |
1,866:08 |