Chapter Status
| Color coding | |
|---|---|
| Completed: | |
| In process: | |
| Not completed: | |
| Chapter | Start | End | Time | Notes |
|---|---|---|---|---|
| Factory | Oct, 2005 | May, 2006 |
Includes:
|
|
| Chapter 3 Education |
Aug 15, 2006 | Sep 25, 2006 | ||
| Chapter 4 Bulkheads |
Nov 19, 2006 | Dec 25, 2006 | 14:00 | Step 1: Front seat back |
| Dec 26, 2006 | Dec 30, 2006 | 19:17 | Step 2: Forward bulkhead |
|
| Jan 01, 2007 | Jan 09, 2007 | 21:38 | Step 3: Instrument panel |
|
| Jan 03, 2007 | May 15, 2007 | 33:06 | Step 4: Landing gear bulkheads |
|
| Jan 04, 2007 | May 19, 2007 | 15:46 | Step 5: Firewall |
|
Chapter hours |
103:47 |
|||
| Chapter 5 Fuselage Sides |
May 21, 2007 | May 25, 2007 | 11:35 | Step 1: Jigs & longerons |
| May 25, 2007 | May 28, 2007 | 21:20 | Step 2: Fuselage forms |
|
| May 30, 2007 | May 31, 2007 | 05:25 | Step 3: Shaping insides |
|
| Jun 1, 2007 | Jun 11, 2007 | 13:25 | Step 4: Longerons |
|
| Jun 10, 2007 | Jun 16, 2007 | 12:40 | Step 5: Lower longerons |
|
| Jun 15, 2007 | Jun 18, 2007 | 13:42 | Step 6: Fuselage sides |
|
Chapter hours |
78:57 |
|||
| Chapter 6 Fuselage Assembly |
June 20, 2007 | Sep 13, 2007 | 44:09 | Step 1: Fuselage build |
| Sep 14, 2007 | Oct 17, 2007 | 36:49 | Step 2: Keel & brace |
|
| Oct 17, 2007 | Oct 30, 2007 | 37:57 | Step 3: Fuselage bottom |
|
Chapter hours |
118:55 |
|||
| Chapter 7 Fuselage Exterior |
Oct 30, 2007 | Nov 7, 2007 | 27:00 | Step 1: NACA scoop |
| Nov 7, 2007 | Dec 15, 2007 | 23:14 | Step 2: Shaping bottom |
|
| Dec 15, 2007 | Dec 23, 2007 | 13:34 | Step 3: Fiberglassing |
|
| Dec 28, 2007 | Jan 3, 2008 | 06:55 | Step 4: Shaping sides |
|
| Jan 3, 2008 | Jan 24, 2008 | 21:10 | Step 5: Fiberglassing |
|
Chapter hours |
91:53 |
|||
| Chapter 8 Headrest & Seatbelts |
Feb 9, 2008 | Feb 9, 2008 | 01:40 | Step 1: Carving foam |
| Feb 10, 2008 | Feb 11, 2008 | 07:43 | Step 2: Fiberglassing |
|
| Feb 10, 2008 | Feb 14, 2008 | 08:58 | Step 3: Shoulder support |
|
Step 4: Making headrests |
||||
| Feb 10, 2008 | Feb 10, 2008 | 01:53 | Step 5: Shoulder harness |
|
| Feb 14, 2008 | Feb 17, 2008 | 14:48 | Step 6: Seatbelts & step |
|
| Feb 17, 2008 | Feb 23, 2008 | 29:28 | Step 7: Seatbelt attach |
|
Chapter hours |
64:28 |
|||
| Chapter 9 Landing Gear & Landing Brake |
Feb 19, 2008 | Feb 26, 2008 | 26:21 | Step 1: Gear bulkhead |
| Mar 10, 2008 | Mar 23, 2008 | 29:11 | Step 2: Start strut install |
|
| Mar 23, 2008 | Jul 15, 2008 | 78:48 | Step 3: Attach tabs |
|
| Jul 17, 2008 | Aug 2, 2008 | 32:41 | Step 4: Landing gear cover |
|
| Aug 2, 2008 | Oct 16, 2008 | 27:33 | Step 5: Axles & brakes |
|
| Oct 10, 2008 | Nov 1, 2008 | 47:29 | Step 6: Landing brake |
|
Chapter hours |
242:03 |
|||
| Chapter 10 Canard |
Jan 23, 2009 | Feb 10, 2009 | 10:25 | Step 1: Cutting the Cores |
| Apr 15, 2009 | May 5, 2009 | 31:30 | Step 2; Lift Tabs & Shear Web |
|
| May 10, 2009 | Jun 30, 2009 | 10:15 | Step 3: Assemble Canard Sections |
|
| Jul 1, 2009 | Jul 5, 2009 | 09:10 | Step 4: Spar Cap Layup |
|
| Jul 7, 2009 | Jul 7, 2009 | 06:29 | Step 5: Apply Bottom Skin |
|
| Jul 9, 2009 | Jul 24, 2009 | 35:42 | Step 6: Hinges, Spar Cap & Top Skin |
|
Chapter hours |
103:31 |
|||
| Chapter 11 Elevators |
Jul 14, 2009 | Aug 3, 2009 | 12:27 | Step 1: Cutting foam cores & bonding to torque tubes |
| Aug 4, 2009 | Aug 4, 2009 | 05:29 | Step 2: Installation of the bottom skin |
|
| Aug 5, 2009 | Aug 9, 2009 | 11:34; | Step 3: Installation of the top skin |
|
| Aug 6, 2009 | Aug 22, 2009 | 19:25 | Step 4: Installing the NC-6 inserts and the NC-3 hinges |
|
| Aug 11, 2009 | Aug 27, 2009 | 22:59 | Step 5: Checking the elevator travel & installing tip farings |
|
| Aug 27, 2009 | Sep 13, 2009 | 15:28 | Step 6: Install pitch trim belcrank & balance weights |
|
Chapter hours |
87:22 |
|||
| Chapter 12 Canard Installation |
Aug 31, 2009 | Aug 31, 2009 | 01:20 | Step 1: Fitting the alignment pins |
| Aug 31, 2009 | Sep 4, 2009 | 11:52 | Step 2: Aligning the canard |
|
| Sep 13, 2009 | Sep 16, 2009 | 04:28 | Step 3: Fitting elevators & torque tube to fuselage |
|
Chapter hours |
17:40 |
|||
| Chapter 13 Nose, Nose Gear & Rudder pedals |
Sep 20, 2009 | Oct 1, 2009 | 05:26 | Step 1: Reinforcing the glass strut |
| Oct 16, 2009 | Nov 13, 2009 | 23:01 | Step 2: Fabrication of the NG-30s |
|
| Dec 27, 2009 | Dec 28, 2009 | 11:10 | Step 3: Installing the electric nose lift |
|
| Dec 29, 2009 | Dec 30, 2009 | 06:54 | Step 4: Installation of the nose box on fuselage |
|
| Jan 9, 2010 | Jan 25, 2010 | 48:08 | Step 5: Adding the nose floor and sides |
|
| Jan 24, 2010 | Jan 26, 2010 | 06:24 | Step 6: Installing the rudder pedals |
|
| Jan 30, 2010 | Mar 30, 2010 | 24:02 | Step 7: Installing the master brake cyclinders |
|
| Apr 6, 2010 | Jan 18, 2011 | 30:49 | Step 8: Completion of the nose gear |
|
| Nov 16, 2010 | Nov 16, 2010 | 03:12 | Step 9: Piping the pitot & static system |
|
| Jan 20, 2011 | Aug 5, 2011 | 78:22 | Step 10: Closing the top & finishing the outside |
|
| Aug 5, 2011 | 18:47 | Step 11: Making the door for the nose compartment |
||
Chapter hours |
256:15 |
|||
| Chapter 14 Center Section Spar |
Aug 15, 2011 | Aug 18, 2011 | 10:35 | Step 1: Center section jig |
| Aug 18, 2011 | Aug 20, 2011 | 3:15 | Step 2: Assembly of foam parts |
|
| Aug 17, 2011 | Aug 29, 2011 | 23:40 | Step 3: Interior layups |
|
| Aug 23, 2011 | Oct 24, 2011 | 25:46 | Step 4: Install the forward face |
|
| Oct 25, 2011 | Oct 29, 2011 | 19:49 | Step 5: Outside hard points |
|
| Nov 11, 2011 | Nov 19, 2011 | 13:14 | Step 6: Spar cap layup |
|
| Nov 24, 2011 | Nov 28, 2011 | 28:10 | Step 7: Shoulder harness & outside layups |
|
| Nov 29, 2011 | Step 8: Hardpoint reinforcements |
|||
Step 9: Access for wing attach and end layup |
||||
Step 10: Installing in the fuselage |
||||
Chapter hours |
94:49 |
|||
| Chapter 15 Firewall |
Step 1: Rudder cable brackets |
|||
Step 2: Firewall insulation & liner |
||||
Chapter hours |
|
|||
| Chapter 16 Control System |
Step 1: Pivot mounts |
|||
Step 2: Fabrication of pitch & roll parts |
||||
Step 3: Assembly of pitch & roll parts |
||||
Step 4: Installation of pitch & roll assembly |
||||
Step 5: Routing & rigging the rudder cables |
||||
Step 6: Rudder stop and brakes |
||||
Chapter hours |
|
|||
| Chapter 17 Trim System & Center Console |
Step 1: Roll trim |
|||
Step 2: Pitch trim |
||||
Step 3: Landing brake and center console; |
||||
Step 4: Throttle quadrant |
||||
Step 5: Landing light |
||||
Chapter hours |
|
|||
| Chapter 18 Canopy |
Step 1: Building the turtleback form |
|||
Step 2: Construction of turtleback & inside layup |
||||
Step 3: Turtleback bulkhead & rib |
||||
Step 4: Contouring & glassing outside of turtleback |
||||
Step 5: Installing the windows |
||||
Step 6: Installing hinges on longerons |
||||
Step 7: Installing upper half of firewall |
||||
Step 8: Installing the turtleback |
||||
Step 9: Engine mount reinforcements |
||||
Step 10: Installing the canopy |
||||
Step 11: Building the canopy frame |
||||
Step 12: Unknown (can't find in the instruction manual) |
||||
Step 13: Canopy hardware reinforcements & inside skin |
||||
Step 14: Provision for removable fuselage top |
||||
Step 15: Canopy hinges; cutting out frame; install drip rail |
||||
Step 16: Installing fuselage top |
||||
Step 17: Canopy lip and instrument cover |
||||
Step 18: Installing access door |
||||
Step 19: Installation of canopy latches |
||||
Step 20: Safety catch |
||||
Step 21: Canopy handle |
||||
Step 22: Canopy stop |
||||
Step 23: Cockpit ventilation |
||||
Chapter hours |
|
|||
| Chapter 19 Wings & Ailerons |
|
|||
|
||||
Chapter hours |
|
|||
| Chapter 20 Winglets & Rudders |
|
|||
|
||||
Chapter hours |
|
|||
| Chapter 21 Strakes & Fuel Tanks |
|
|||
|
||||
Chapter hours |
|
|||
| Chapter 22 Electrical |
|
|||
|
||||
Chapter hours |
|
|||
| Chapter 23 Engine |
|
|||
|
||||
Chapter hours |
|
|||
| Chapter 24 Covers & Fairings |
|
|||
|
||||
Chapter hours |
|
|||
| Chapter 25 Finishing |
|
|||
|
||||
Chapter hours |
|
|||
| Chapter 26 Upholstery |
|
|||
|
||||
Chapter hours |
|
|||
| Phase 1 Flight Testing |
|
|||
|
||||
Chapter hours |
|
|||
Total Hours |
1,259:40 |
|||